What's New

DaChan Bay Terminals becomes the first container terminal in Shenzhen providing shore power at all berths

23 October 2019

The smooth running of the shore power system at DaChan Bay Terminals for HMM PROMISE for over 10 hours earlier in the month marked the completion of the second phase of the terminals’ project to provide greener energy to vessels berthing at its facilities. This makes DaChan Bay Terminals the first container terminal in Shenzhen with all berths featuring shore power capability.

DaChan Bay Terminals and HMM place great importance on this test run and an engineering team of HMM’s supplier has specially flown into Shenzhen for the occasion.  The success of the test run reflects the high stability, reliability, and safety of the system at DaChan Bay Terminals laying solid foundation for regular usage.

The construction of the second phase of the shore power supply system commenced on 25 February 2019 and completed in late September this year.